Highway 95 Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

(Prepared July 9, 2026)

    • The project has moved into Phase 2 and Detour B is in place (see Detour B map below):
      • Hwy 95 is closed west of Main Street –
        • Detour Signage changes:
          • 2nd Ave SW thru 10th SW are signed as “Closed to thru traffic” between Main St. and Dellwood (open to residents)
        • ALL DETOUR TRAFFIC IS TO FOLLOW DETOUR Route B, listed below  
      • Garfield St. (Hwy 95 at McDonalds) to 11th Ave S. to Dellwood St to 2nd Ave SW is the detour route until October
      • Fern Street is open across Hwy 95

Either Birch Street or Cypress Street will also be open across Hwy 95 during this phase 

Pedestrian route is 2nd Ave NW to Main Street, follow signage 

Residents and businesses with project questions are encouraged to call the Project Hotline 320.204.1762

 The project will be completed over 2 years.  See map for project phasing and schedule

For the latest project updates and to be included in email updates from MnDOT visit their project website: Hwy 95 Cambridge - 2026-2027 construction - MnDOT


The project work planned for 2026 will be broken into 2 segments

Segment 1 – Fern Street to Dellwood – Construction planned April 20th to mid-summer

Segment 2 – Dellwood Street to Main – Construction planned Mid-summer to October

A project location map and detour maps are posted on the MnDOT’s website: Hwy 95 Cambridge - 2026-2027 construction - MnDOT

The improvements include the following:

  • Replacing the existing concrete curb and pavement.
  • Replacing the existing sanitary sewer, water main and storm sewer.
  • Installing new sidewalks on both sides of TH 95
  • Replacing the existing signal systems at Fern St., Dellwood St., Main St., and Fillmore St.
  • Replacing the Railroad crossing surface
  • Replacing the decorative lighting system in the downtown area
  • Reconstructing TH 95 from 3-lanes to 4-lanes with a center median from Main Street to Fillmore Street to match the existing 4-lane section on the east side of the City
  • Relocating the existing train switch for Federated Propane to the south end, to reduce trail crossing delays on TH 95 – Will be completed in 2027
  • Relocating and installing some new streetlights outside of the downtown area for a uniform system.

Access:  In general, the Contractor will provide access to all properties during construction. When pipe and curb installation is done directly in front of a property, then driveway access will not be possible.  The Contractor will provide advance notice of this, and temporary parking arrangements will be reviewed. 


Detour Information

Detour B Revised