2020 Street Improvement Project

Print
Press Enter to show all options, press Tab go to next option

16th Avenue SE to close - June 1 until June 15

16th Avenue SE will be closed to traffic for safety reasons from Joe's Lake Road to Old Main Street South while reconstruction activities take place. Click here for a map of the closure area and the detour route.

Cambridge 2020 Street Improvements Construction Update

Prepared May 26, 2020

16th Ave SE (Old S. Main St to Joe’s Lake Rd):

  • The pipe crew is continuing installing new storm sewer pipe which will continue next week.
  • Road grading is planned to begin late this week and continue most of next week.
  • Curb and gutter installation is planned for late next week or early the following week.

 Old S. Main St:

  • Private underground utilities (gas, electric, phone, telecom) are continuing their relocation work in preparation for the road reconstruction to begin. 

18th Ave SE & Southhaven Dr:

  • The gravel road will be graded and some spot replacement of damaged curb and gutter is planned for next week.  

 Main St from 3rd Ave S to 24th Ave S:

  • The first phase of work is continuing on the west half of the road.
  • Milling off the top layer of asphalt will begin tomorrow and take two days to complete. 
  • Repaving the top portion of asphalt is planned for Friday and Saturday.

Cambridge Library:

  • Paving the first layer of asphalt in the parking lots is planned for Thursday.

 

Prepared May 19, 2020

16th Ave SE (Old S. Main St to Joe’s Lake Rd):

  • The pipe crew is installing new storm sewer pipe which will continue next week.
  • Road grading will be done after the pipe is complete.

 Old S. Main St:

  • Private underground utilities (gas, electric, phone, telecom) are continuing their relocation work in preparation for the road reconstruction to begin. 

18th Ave SE & Southhaven Dr:

  • Fire hydrants have been replaced. 
  • The gravel road will be graded and some spot replacement of damaged curb and gutter will be done next.  

 Main St from 3rd Ave S to 24th Ave S:

  • The first phase of work is continuing on the west half of the road.
  • Concrete sidewalk pedestrian ramp work is now complete.
  • Deteriorated manhole and catch basin castings are being repaired this week.
  • Boulevard restoration is planned for this week.
  • Milling and repaving the top portion of pavement is scheduled to be begin next Tuesday May 26. This will take about a week to complete. 

Cambridge Library:

  • Parking lot curb is complete. 
  • Remaining sidewalk is being done today. 
  • Boulevards are being restored. 
  • Lot paving is planned next week.
2020StreetImprovementProject_Detour1024_1

Schedule

Work Schedule

May 5 to June 5, 2020

Work begins on Main Street South between 3rd Avenue S and 24th Avenue S with a mill and overlay project. The work will be done under traffic so please expect minor delays. Finding an alternate route is recommended.

Work will also begin on the parking lots, sidewalks, curb, and gutter at the Cambridge Public Library.

May 5 to September 4, 2020

16th Ave and Old S. Main Street
Private utilities will first work to relocate their equipment. After the private utilities are out of the way, road reconstruction will begin around May 11.

Work will also begin on the Central Greens pickleball courts.

June 2020

28th Avenue and South Haven Drive Reconstruction work begins

Area Work is Happening

16th Avenue SE

Reconstruct the street with curb and gutter similar to Opportunity Boulevard (One lane in each direction with a center left turn lane).  A new storm sewer system to replace the ditches. Some new sanitary sewer and water main to provide service to all adjacent properties. Reconstruction of the trail including a new section under the Highway 65 bridge. New street lighting.

Old South Main Street

Reconstruct the street with curb and gutter (one lane in each direction). A new storm sewer system to replace the ditches. Old water main replacement from 16th Avenue SE to just south of 18th Avenue SE. Reconstruct the trail. New Street Lighting.

18th Avenue SE & South Haven Drive

Replace the existing pavement.Repair damaged sections of curb and gutter and storm sewer. New street lighting.

Carriage Lane north of 16th Ave

Most of the street will be patched with a paver to help this street last until it is reconstructed.This is a maintenance activity and being done with the project since it is more effective than patching by hand.

South Main Street from 3rd Ave S to 24th Ave S

Mill off the top 2” of pavement and replace.Replace some pedestrian ramps and minor traffic signal work at 11th Avenue S to meet current standards.

Peterson Park

Reconstruct the parking lot and trails.Replace the trail lighting.

Central Greens Park

Adding new pickleball courts and a half-basketball court on the west side of the existing courts.

General Information

Construction Process: The construction process will follow this general pattern: Pulverizing the existing pavement, removing the existing curb, replacing underground sanitary sewer, water main, and services to lots, replacing and installing some new storm sewer, grading for the new street, installation of curb & gutter, asphalt base course paving, sidewalk installation,  sod restoration and then final asphalt wearing course paving.  Private utilities (Gas, electric, phone and cable TV) will also be performing some work on their facilities during the project. 

  1. Tree removal: Care will be taken to save trees where feasible, but some trees near the street will need to be removed due to these improvements. The removals will be kept to a minimum, and the property owner will have the option of having the tree replaced on private property near the street.Property owners will be allowed to select a type of tree from a pre-approved list.

  2. Pulverizing existing pavement: The contractor will start with a machine to grind up the existing street pavement into gravel in most areas.This gravel material will then be salvaged for use on the project.After this is done, any existing concrete curb that needs to be replaced will be removed.

  3. City underground pipe work: After the existing gravel is salvaged, the contractor will start work on the City’s underground utility pipes (storm sewer, sanitary sewer and water main). During this time, there will be continual sanitary sewer service and some minimal disruption in water service where water main is being replaced on Old South Main Street.The contractor will provide temporary water service connections to properties in this water main replacement area. 

  4. Grading and curb & gutter: After the underground pipes are installed, another crew will start grading the road and preparing it for gravel.The contractor will then place enough gravel to be able to construct the concrete curb and gutter.Properties with direct access to Old South Main Street and 16th Avenue will be given notice when the curb and gutter is to be installed so they can move your vehicles out of the driveway for 5-6 days as the concrete cures.Commercial drives will likely be done half at a time since they are wider and to maintain business access. We ask that vehicles be parked elsewhere during the day of curb construction.After that they will be able to be parked in front of the property alongside the new curb during the 5-6 days that it takes for the concrete to cure.After this the contractor will backfill behind the curb to protect it. Trail construction will follow the curb construction as soon as possible.

  5. Asphalt base course paving: After the curb has cured, the first layer of asphalt will be paved.

  6. Restoration: The contractor will begin to grade behind the curb after the curb has cured to match your property to the curb elevation. If you had a tree removed on your property, you will have the option of having it replaced at this time. Topsoil and seeding or sod will be then be done. It is very important to water any sod so that it takes root and survives.The Contractor will help water it for the first three weeks, but after that it is the property owner’s responsibility to maintain. There will be no sod replacement. Please help water your sod so it survives!

  7. Final asphalt wearing course paving: After the restoration work is complete, street signs will be installed and the final layer of asphalt will be paved.

  8. Private utility work: A number of utilities (gas, electric, phone, cable, etc.) will be replaced or relocated throughout this year’s project area.This work is necessary for the proposed utility and street construction.The private utilities will have their own crews or will hire their own subcontractors to do this work.

Communication and cooperation will help this project be successful for all. If you have an event scheduled (graduation, open house, garage sale, etc.) please contact a representative below prior to the event and we can work with the contractor to coordinate access. If you experience any disruption in services (water, power, phone, etc.) during the construction period, please contact someone on the below list right away.  The sooner we are aware of an issue with service, the sooner we can work with the contractor or utility company to correct the disruption